Power interruptions in the CRTD building (beendet)
From: 26.11.2024 / 06:00
To: 27.11.2024 / 17:00
November 26:
Blackout test, including involvement of the diesel generator (entire building, the UPS of the distribution and server room is not affected)
Test of the emergency power supply (floor by floor)

November 27:
Test of the “normal” power supply including insulation test of the installed cables, also leads to failure of the emergency power supply (floor by floor)

--